Acted for the CERC before the Supreme Court in a batch of appeals filed under Section 125 of the Electricity Act, 2003 challenging the treatment of depreciation by APTEL while fixing the tariff for various National Thermal Power Corporation (‘NTPC’) power stations.

Electricity Generation
Case 1
Electricity Generation
Case 2
Acted for Jaiprakash Power Ventures Ltd. (JPVL) before the MPERC and APTEL in relation to the treatment of additional levy on coal imposed by the Supreme Court and pass through of cost of mining and additional premium payable on coal under the terms of the auction carried out by the Government of India.


Electricity Generation
Case 3
Acted for various Renewable and Conventional Power Generation Companies on matter related to regulatory approval and change in law provisions before CERC & SERC’s.
Electricity Generation
Case 4
Represented various Renewable Power Developers in a dispute before the CERC in relation to re-opening of the PPAs executed with NTPC Vidyut Vyparan Nigam Limited for seeking revision of the bid-out tariff specified under the PPAs.


Electricity Generation
Case 5
Advised and represented various Renewable Power Developers before High Court of Bombay and MERC in proceedings related to re-classification of wind zones in the State of Maharashtra.
Electricity Generation
Case 6
Advised and represented various Renewable Power Developers before different forums in proceedings challenging the forecasting, scheduling and deviation settlement mechanism notified by the Maharashtra and Rajasthan Electricity Regulatory Commissions.


Electricity Generation
Case 7
Acted for Lanco Kondapalli before CERC in relation to challenging the method of computation of zonal PoC charges under the CERC Regulations for Sharing of Transmission Charges and Losses.
Electricity Generation
Case 8
Acted for Lanco Kondapalli Power Ltd. before the Supreme Court in a matter that led to a landmark judgment on the applicability of the laws of limitation to the Electricity Act, 2003.


Electricity Generation
Case 9
Acted for Clean Wind Power Limited in writ petitions filed before Karnataka High Court on behalf of captive consumers contesting demand of CSS for consumption from the CGP own and operated by CWP (Manvi) Ltd.
Electricity Generation
Case 10
Acted for West Bengal Power Development Co. Ltd. (WBPDCL) in an investigation initiated by the central bureau of investigation on improper allocation and usage of coal block.


Electricity Generation
Case 11
Acted for WBPDCL before APTEL in a number of matters challenging WBERC orders determining the generation tariff for WBPDCL.
Electricity Generation
Case 12
Acted for Lanco Amarkantak Power Ltd. before the CERC in a proceeding filed by PGCIL for cancellation of open access of PTC through whom Lanco was supplying power due to non-submission of payment security.


Electricity Generation
Case 13
Advised Jindal Group on the structuring of investments in captive power plant and applicability of cross subsidy surcharge.
Electricity Generation
Case 14
Acted for Essar Power before CERC in a tariff petition filed by Power Grid Corporation.


Electricity Generation
Case 15
Advised an integrated power utility in restructuring its power and other business verticals including demerger of its generation and distribution verticals and preparation of necessary transaction documents.
Electricity Generation
Case 16
Acted for Lanco Solar before CERC in a petition seeking re-adjustment of the commissioning date and tariff fixed under a competitive bidding process held under the Jawaharlal Nehru National Solar Mission.


Electricity Generation
Case 17
Represented several Captive Power Producers before the High Court of Punjab & Haryana against the imposition of electricity duty by the State Government.
Electricity Generation
Case 18
Advised Essar Power Limited on the issue of relinquishment and strategizing to mitigate the contractual and financial implications and build a case for force majeure affecting the operationalization of the open access.


Electricity Generation
Case 19
Acted for Himachal Sorang Power Ltd. before CERC for extension of the date for commencement of open access under the BPTA.
Electricity Generation
Case 20
Acted for Hindustan Power Pvt Ltd (earlier named as Moser Baser Power Pvt Ltd.) and its subsidiaries in relation to various regulatory issues with respect to its solar, thermal and hydro power projects before different adjudicatory forums.


Electricity Generation
Case 19
Acted for Udupi Power Company Ltd before the CERC in a matter relating to determination of generation tariff.